SCHOOL, FRINDSBURY
We were first contacted in early August to give advise on this 360m2 wall. By the end of the following month, we had provided the school with a full design and accompanying construction information, manufactured the blocks, delivered them to site, carried out site visits and signed off their groundworkers' installation work.
Colin Gaunt, Concrete & Rock Solutions




360m StaBlock wall area
2



27m average daily install rate
2



3 man team



14 days total install time
Frindsbury School: Overview
Frindsbury School: Foundation installation
Frindsbury School: First Day of Block Installation
Frindsbury School: Overview
1/3