SCHOOL, FRINDSBURY

We were first contacted in early August to give advise on this 360m2 wall. By the end of the following month, we had provided the school with a full design and accompanying construction information, manufactured the blocks, delivered them to site, carried out site visits and signed off their groundworkers' installation work.

​

​

Colin Gaunt, Concrete & Rock Solutions

Capture.JPG

360m   StaBlock wall area

2

27m   average daily install rate

2

3 man team

14 days total install time