top of page
QUARRY, ORLEANS (FRANCE)
We were first contacted about this project on 10th July. 53 days later we had provided the client with a full design and accompanying construction information, manufactured the blocks, delivered them to site, carried out site visits and signed off their groundworkers' installation work.
​
​
Colin Gaunt, Concrete & Rock Solutions




1,150m StaRock wall area
2



32m daily install rate
2



3 man teams



15 days total install time

Orleans Quarry

Orleans Quarry: Stepped Section

Orleans Quarry
1/2
bottom of page