QUARRY, ORLEANS (FRANCE)

We were first contacted about this project on 10th July. 53 days later we had provided the client with a full design and accompanying construction information, manufactured the blocks, delivered them to site, carried out site visits and signed off their groundworkers' installation work.

​

​

Colin Gaunt, Concrete & Rock Solutions

Capture.JPG

1,150m   StaRock wall area

2

32m   daily install rate

2

3 man teams

15 days total install time